Replace all antiacid brick flooring, covering a surface of more than 25,000 square feet, in less than 14 days. It is important to stress that the production line in the factory involved was made up of massive, very heavy machinery and equipment.


Each piece of equipment in the production line was hung from the roof’s structural beams to free the floor surface. The work was then performed section by section.


The time allowed for work stoppages was respected, which enabled this milk and cheese producer to retain its milk quotas. Otherwise, the company’s viability could have been threatened.